Kolkata Metro Line 2

Kolkata Metro Line 2, also known as the East-West Metro and Green Line, is a rapid transit line of the Kolkata Metro in the Indian state of West Bengal. It currently consists of two distinctly operational sections between Salt Lake and Sealdah, and Esplanade and Howrah Maidan by going underneath the Hooghly River, with an eastern extension planned for Teghoria.[1][7] It will cover a distance of 32.11 km (19.95 mi) and consist of 17 stations from Teghoria (Haldiram) in the east to Howrah Maidan in the west, of which it will consist of 11 elevated and 6 underground stations, and the operational section consists of 6 elevated and 6 underground stations, with a total distance of 22 km (14 mi). It is expected to derive a very high ridership, since it will connect India's two largest commuter railway and long-distance railway terminals, Howrah and Sealdah, along with two of its largest business districts, BBD Bagh and Salt Lake Sector V. At present, more than 100,000 passengers commute through the line every day, and this figure is expected to go up to 1 million after it gets fully completed by 2035.[5] It will also connect the industrial hub of Kolkata, i.e., Howrah and the IT hub of Kolkata, i.e., Salt Lake Sector-V.[9] It connects Line 1 at Esplanade and will eventually connect Lines 3 and 6.

The Line 2 has India's first and biggest underwater metro tunnel, along with the deepest metro ventilation shaft.[10][11] In the deepest metro shaft, the Howrah metro station is be the deepest metro station in India, at a depth of 33 m (108 ft).[12] The first phase between Salt Lake Sector V and Salt Lake Stadium was inaugurated by the then Minister of Railways, Piyush Goyal, on 13 February 2020, and commercial services started from 14 February 2020.[6][13] The underground stretch till Phoolbagan was opened on 4 October 2020 by the current Minister of Railways, Ashwini Vaishnaw, and then till Sealdah was opened on 12 July 2022.[14][15] The section between Esplanade and Howrah Maidan was inaugurated by Prime Minister Narendra Modi on 6 March 2024,[16] leaving the gap between Esplanade and Sealdah as the only remaining unopened section.

History

The master plan had already identified the corridor way back in 1971. But the success of the Delhi Metro contributed to the sanction of the East–West Metro corridor, which would connect Howrah railway station with the satellite city of Salt Lake. In January 2004, the Vadodara-based Pacific Consultant International Group conducted a feasibility study for the line. The report proposed the route and tubular structures be under the Hooghly River, a distributary of the Ganga River.

A new organisation called the Kolkata Metro Rail Corporation Limited (KMRCL) was formed, which would be executing the operations of this line, by commencing construction in 2009.[17] Of the KMRC's eight directors, four each were from the Governments of West Bengal and India. The cost was being shared between the state government as 30 percent, the Union Urban Development Ministry as 25 percent, and the Japan Bank for International Cooperation (JBIC) as 45 percent.[18] But in 2011, after state government disinvested from the project, most of the share of this project went to Indian Railways, the owner of the Kolkata Metro, and with the JBIC. The project is estimated at a cost of 5,000 crore (US$600 million).[19] While by 2019, the cost escalated to 8,000 crore (equivalent to 99 billion or US$1.2 billion in 2023).

Due to major setbacks, such as land acquisition, slum relocation, and route alignment problems, the project got delayed. The East-West Corridor was originally slated to be operational by 2012, but was later pushed back to 2015. The project was implemented in four phases. The first phase, from Salt Lake Sector V to Salt Lake Stadium, became operational on 13 February 2020.[6] The second phase, to Phoolbagan opened on 4 October 2020.[14] The third phase to Sealdah became operational from 14 July 2022,[15] and part of the final phase between Esplanade and Howrah Maidan, which includes the journey through the tubular tunnels under the Hooghly River, became operational on 6 March 2024. This made the line and the Kolkata Metro the first metro to run underwater in India,[7][20] leaving the gap between Esplanade and Sealdah as the only remaining unopened section of the line.

Just before the tunnel enters the underwater segment, lies a ventilation shaft on the Kolkata bank of Hooghly River, which is the deepest of its kind in India, at 44 metres (144 ft) below ground level.[21]

Current status

Artists Conception of East west underwater metro at Esplanade Metro station
East west metro tunnel underwater section

As of March 2024

East–West tunnel section – part of Line 2 – of the Kolkata Metro under the river Hooghly River,

Stations

Inauguration

1st phase

On 3 February 2020, the final inauguration date was revealed. After 11 years, since the construction started, the first phase of the line was inaugurated on 13 February by Union Minister of Railways Piyush Goyal, with commercial services to start the very next day. The service will start from 8 am and ends at 8 pm, with 37 pairs of services a day. 5 rakes would run at a frequency of 20 minutes. Dipak Kumar drove the first train.[31][32][33][34][35]

In October 2021, services up to Phoolbagan were extended as a part of Phase 1A.

2nd Phase

On 14 July 2022, the first commercial run from Sealdah metro station was made, as a part of Phase 2.[36]

3rd phase

Prime Minister Narendra Modi inaugurating the Esplanade–Howrah Maidan stretch of the line on 6 March 2024 from Esplanade metro station

On 6 March 2024, the truncated route between Esplanade and Howrah Maidan was inaugurated by Prime Minister Narendra Modi.[20]

Infrastructure

Stations

All the stations in this line are equipped with Platform Screen Doors to keep people away from the tracks for greater safety.[37] Mott MacDonald is the detailed design consultant for all the elevated stations, whereas Lee Harris Pomeroy Architects have designed all the underground stations. Out of the 6 underground stations, 3 have been built by ITD Cementation, a part of the Italian-Thai Development Public Company, and the other 3 by Afcons Infrastructure, including the 520 meters underwater stretch. All the elevated stations were built by Kolkata-based Simplex Infrastructure ltd.[38][39]

Escalators and elevators

90 escalators and 40 elevators have been installed at different levels in the line to facilitate smooth mobility of passengers, including physically challenged and aged persons. The Letter of Award (LoA) for installation of forty-one escalators and twenty-six elevators for 8 stations of Phase-I has been awarded.[40]

Tunnel Ventilation System (TVS)

TVS provides a means to control smoke flow and ensure safe evacuation of passengers in case of a fire, as well as maintain an acceptable environment in the tunnel and station track ways. The Tender for the TVS was invited and the bids of eligible tenderers have been evaluated.

Platform Screen Doors at the Salt Lake Stadium metro station

Platform Screen Doors (PSDs)

The PSDs are a system of full height/half height motorized sliding doors that provide controlled access to the trains and protect the platform edges. The PSD work for 6 elevated and 6 underground stations have been completed.

Electrification, signaling and automatic fare collection

The line has two types of signaling equipment supplied by ANSALDO STS. One is the feature cab signaling and another is the continuous automatic train control with automatic train protection. The other signaling equipment includes an integrated system featuring a fiber optic cable, SCADA, radios and a PA system. The line also has a train information system, control telephones and a centralized clock system. The contract for AFC works has been awarded to M/s. Indra Sistemas SA (Spain).[40]

Operations

Unlike the north–south corridor, the east–west metro will run from 8 am to 8 pm at a frequency of 1.5 minutes during peak hours and 5 minutes during non-peak hours.[41] But in phase 1 operations, the frequency will be 20 minutes, and each will stop for 20 seconds in each station.[42]

Rolling stock

The interior of the East-West Metro rake

The Construcciones y Auxiliar de Ferrocarriles (CAF), in collaboration with Melco, was to supply 14 trains for this line.[43] The 14 rakes were acquired at a cost of approximately €110m 600 crore (US$72 million).[8] Each rake composes of 6 coaches having a capacity of 2,068 people per train.[43] The maximum speed of the train is 90 km/h (56 mph). The first lot of trains was to be manufactured in Spain and imported to Kolkata in November 2014. The next lot was to be manufactured in India. However, the tender was cancelled by the Kolkata Metro Rail Corporation (KMRC) due to technical reasons,[44] and excessive delay in project. Then, a re-tender was issued in July 2015. The Bharat Earth Movers Limited (BEML) emerged as the only bidder in the fourth round of bidding for providing the rolling stock.[45] Thus, the contract for providing the rakes was awarded to the BEML.[46] The BEML has earlier provided rakes for Delhi Metro, Bengaluru Metro and Jaipur Metro. Fourteen rakes, each with six coaches, were ordered. Out of 14, 11 rakes have already been received by the KMRC.

Tunnel lights

In December 2023, Kolkata Metro added blue light in the underwater tunnel section to give passengers a sense of feeling under Hooghly River alongside other lights in the tunnel.[47]

Proposed extensions

The Government of West Bengal has proposed an extension to the East–West Metro line. In this proposal, the line will be connected again to the Dum Dum Airport of the New Garia Metro in Teghoria (Haldiram). According to this proposal, the East-West Metro will have 3 terminating stations at Howrah Maidan, Salt Lake Sector-V and the proposed Teghoria station. In Teghoria, it will be connected to the NSCBI Airport-New Garia metro route (VIP Road station), and interconnection facilities will be present. It was previously planned that the extension and the present route would converge at the Central Park Station.[48] But now the plan is changed and it is decided to extend the line directly from Salt Lake Sector V Station.[49] The proposed extension is under study and it will need several clearances before being implemented. Another 10 km (6.2 mi) East-West Metro extension project from Howrah Maidan to Santragachi bus terminus has also been proposed. Rail India Technical and Economic Service (RITES), and the implementing agency for this project was planned to start work on the corridor early in 2017.[50]

Timeline

Gallery

See also

References

  1. ^ a b "New System Map of Kolkata Metro". Archived from the original on 5 September 2019. Retrieved 20 July 2019.
  2. ^ "East-West load on struggling Metro". Archived from the original on 23 July 2019. Retrieved 23 July 2019.
  3. ^ Chakraborty, Ajanta (15 February 2020). "On Valentine's Day, Kolkata falls in love with East-West Metro as trains start rolling out". The Times of India. Archived from the original on 18 February 2020. Retrieved 28 February 2020.
  4. ^ Chakraborty, Ajanta (29 February 2020). "'World-class' East-West Metro still wows Kolkata but crowd thins in 14 day". The Times of India. Archived from the original on 29 February 2020. Retrieved 29 February 2020.
  5. ^ a b "Kolkata East West Metro will ferry 1 million people a day by 2035: Railway official". 25 July 2019. Archived from the original on 25 July 2019. Retrieved 25 July 2019.
  6. ^ a b c "Kolkata Metro gets its second corridor after 36 years. See photos". 13 February 2020. Archived from the original on 14 February 2020. Retrieved 14 February 2020.
  7. ^ a b c d "PM Modi inaugurates India's first underwater metro line in Kolkata". Moneycontrol. 6 March 2024. Retrieved 6 March 2024.
  8. ^ a b "CAF to supply Kolkata metro trains". Archived from the original on 16 August 2014. Retrieved 11 October 2013.
  9. ^ "Kolkata Metro Rail Corporation Ltd".
  10. ^ "Kolkata Metro's TBM S639 Crosses Halfway Mark Under Hooghly". The Metro Rail Guy. 5 May 2017. Retrieved 14 February 2023.
  11. ^ Howrah—Sealdah Metro Link Update || Kolkata East-West Metro || MetroRail Blog, archived from the original on 6 October 2019, retrieved 12 September 2019
  12. ^ "India's first underwater train to be operational by 2023 in Kolkata - Kolkata Metro Rail Corporation train".
  13. ^ a b c "১৩ ফেব্রুয়ারি চালু হচ্ছে ইস্ট-ওয়েস্ট মেট্রো, জেনে নিন ভাড়া তালিকা..." bengali.news18.com (in Bengali). 3 February 2020. Archived from the original on 3 February 2020. Retrieved 3 February 2020.
  14. ^ a b c "(Pics) Kolkata Metro's Phoolbagan Extension of Line-2 Inaugurated". The Metro Rail Guy. 4 October 2020. Retrieved 6 March 2024.
  15. ^ a b "Kolkata Metro Line-2's Sealdah Station Inaugurated". The Metro Rail Guy. 12 July 2022. Retrieved 6 March 2024.
  16. ^ Chakraborty, Ajanta (6 March 2024). "India's first under-river Metro becomes reality". The Times of India. Retrieved 6 March 2024.
  17. ^ "East-West Metro gets new boss". The Telegraph. Archived from the original on 2 November 2012. Retrieved 1 July 2011.
  18. ^ "East-West Metro's route likely to change". Business Standard.
  19. ^ Pramanik, Abhishek Law, Ayan (17 July 2012). "Kolkata Metro inks purchase pact for coaches for East-West corridor". Archived from the original on 27 September 2013. Retrieved 5 August 2012.{{cite web}}: CS1 maint: multiple names: authors list (link)
  20. ^ a b c "PM Modi unveils multiple metro projects, including Kolkata underwater corridor". The Hindu. 6 March 2024. Retrieved 6 March 2024.
  21. ^ East-West Metro, Kolkata (2024), retrieved 8 March 2024
  22. ^ a b "Kolkata: New Sealdah metro station is all set to be inaugurated today, commercial operations to start on July 15". 11 July 2022.
  23. ^ "Hope for ops start of three new Metro links in March first week". The Times of India. 19 February 2024. ISSN 0971-8257. Retrieved 21 February 2024.
  24. ^ Hossain, Shaheryar (1 December 2020). "Outer structure of Esplanade Metro Station completed". www.millenniumpost.in. Retrieved 20 May 2021.
  25. ^ Ajanta Chakraborty (24 February 2020). "Kolkata: After work for 29 months, station structure ready at Mahakaran | Kolkata News - Times of India". The Times of India. Retrieved 20 May 2021.
  26. ^ a b Ajanta Chakraborty (16 May 2021). "12 years and several stumbling blocks later, E-W Metro tunnelling work is complete | Kolkata News - Times of India". The Times of India. Retrieved 20 May 2021.
  27. ^ "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 March 2024.
  28. ^ "India's deepest Metro station at Howrah also to be the largest". The Times of India. 1 March 2024. ISSN 0971-8257. Retrieved 8 March 2024.
  29. ^ "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 March 2024.
  30. ^ "Howrah metro station is India's deepest subway". Constro Facilitator. 20 August 2019. Archived from the original on 20 February 2020. Retrieved 20 February 2020.
  31. ^ a b c Chakraborty, Ajanta; Gupta, Jayanta (5 February 2020). "8am on Valentine's Day; Your date with East-West Metro". The Times of India. Archived from the original on 5 February 2020. Retrieved 5 February 2020.
  32. ^ "Kolkata Metro: East-West Metro railway set to roll out on 13 February". Livemint. 4 February 2020. Archived from the original on 5 February 2020. Retrieved 5 February 2020.
  33. ^ a b Singh, Neha (5 February 2020). "Kolkata East-West Metro is all set to begin Operations on 13th February". Metro Rail News. Archived from the original on 5 February 2020. Retrieved 5 February 2020.
  34. ^ "আজ উদ্বোধন ইস্ট-ওয়েস্ট মেট্রোর". Anandabazar Patrika (in Bengali). 13 February 2020. Archived from the original on 13 February 2020. Retrieved 13 February 2020.
  35. ^ Chakraborty, Ajanta (12 February 2020). "West Bengal: This is how your journey through Salt Lake will be from Valentine's Day". The Times of India. Archived from the original on 14 February 2020. Retrieved 20 February 2020.
  36. ^ "Kolkata takes a first look at Sealdah Metro station after inauguration". www.telegraphindia.com. Retrieved 14 July 2022.
  37. ^ "KMRC=2013-07-22". Archived from the original on 4 June 2013. Retrieved 22 July 2013.
  38. ^ "Mott MacDonald is detailed design consultant on Salt Lake City Stations". Archived from the original on 26 July 2010. Retrieved 22 July 2013.
  39. ^ "Railway Technology". Archived from the original on 4 August 2013. Retrieved 22 July 2013.
  40. ^ a b "REVIEW OF ANNUAL REPORT AND AUDITED ACCOUNTS OF KOLKATA METRO RAIL CORPORATION LIMITED (KMRCL) FOR THE YEAR 2016-17" (PDF). Archived (PDF) from the original on 9 December 2019.
  41. ^ "Kolkata East West Metro". The Times of India. Retrieved 22 July 2013.
  42. ^ Chakraborty, Ajanta (11 June 2019). "Kolkata East-West Metro trains to ply every 20 mins, stop for 20 secs at each station". The Times of India. Archived from the original on 26 December 2019. Retrieved 28 June 2019.
  43. ^ a b "CAF-Construcciones y Auxiliar de Ferrocarriles, your railway solutions". Archived from the original on 19 October 2014. Retrieved 11 October 2013.
  44. ^ "Kolkata loses Spanish Rides". The Telegraph. Archived from the original on 30 January 2016. Retrieved 2 January 2016.
  45. ^ "Bid saves Metro blushes". The Telegraph (Calcutta). Archived from the original on 31 January 2016. Retrieved 25 January 2016.
  46. ^ "Central PSU wins Rs 900-crore Metro rake order". The Times of India. Archived from the original on 22 January 2016. Retrieved 25 January 2016.
  47. ^ a b Riding UNDERWATER METRO under HOOGHLY RIVER, Kolkata, retrieved 31 December 2023
  48. ^ "East-West eyes easy route to airport". The Telegraph (Calcutta). Archived from the original on 19 February 2016. Retrieved 18 February 2016.
  49. ^ "Kolkata Metro Official Map". Archived from the original on 5 September 2019. Retrieved 20 July 2019.
  50. ^ "2017 start for Howrah EW Metro". The Times of India. Archived from the original on 4 December 2016. Retrieved 3 December 2016.
  51. ^ "Metro to connect Sector V to Salt Lake Stadium soon". Millennium Post. Archived from the original on 28 February 2018. Retrieved 28 February 2018.
  52. ^ "First look at East-West Metro rake". The Telegraph. Archived from the original on 8 May 2018. Retrieved 8 May 2018.
  53. ^ "East West Metro's six-car rake takes first test run at depot". Times of India. Archived from the original on 16 July 2018. Retrieved 21 June 2018.
  54. ^ "E-W Metro ready for trial run between Central Park & Sec V". Times of India. Archived from the original on 27 July 2018. Retrieved 4 July 2018.
  55. ^ "Calcutta Metro's slow-mo stretch". The Telegraph. Archived from the original on 20 December 2018. Retrieved 20 December 2018.
  56. ^ "Another eight joists to be removed before TBMs restart". Times of India. Archived from the original on 20 December 2018. Retrieved 20 December 2018.
  57. ^ "Firm insists on 1000 hours of trial for glitch-free Metro". The Telegraph. Archived from the original on 31 May 2019. Retrieved 31 May 2019.
  58. ^ Chakraborty, Ajanta (18 May 2019). "Kolkata: East-West Metro gets rail board nod". The Times of India. Archived from the original on 29 September 2019. Retrieved 3 September 2019.
  59. ^ "Kolkata: Underground trials at Phoolbagan on Friday". The Times of India.
  60. ^ Chakraborty, Ajanta (7 July 2019). "Two East-West Kolkata Metro stations get fire nod for a year". The Times of India. Archived from the original on 18 July 2019. Retrieved 7 July 2019.
  61. ^ "East-West load on struggling Metro". www.telegraphindia.com. Archived from the original on 23 July 2019. Retrieved 24 July 2019.
  62. ^ Chakraborty, Ajanta (30 July 2019). "Post fire nod, East-West eyes pre-Puja start to services". The Times of India. Archived from the original on 15 August 2019. Retrieved 30 July 2019.
  63. ^ a b c d Chakraborty, Ajanta (17 November 2019). "East-West Metro races against time to meet November 30 deadline". The Times of India. Retrieved 3 February 2020.
  64. ^ Chakraborty, Ajanta (13 August 2019). "India's deepest Metro station comes up 30m below Howrah railway station | Kolkata News - Times of India". The Times of India. Archived from the original on 2 September 2019. Retrieved 13 August 2019.
  65. ^ Chakraborty, Ajanta (21 August 2019). "Kolkata East-West Metro starts its underground trial runs till Sealdah station". The Times of India. Archived from the original on 29 September 2019. Retrieved 3 September 2019.
  66. ^ "Kolkata: Homes emptied after cracks in Calcutta's Bowbazar". The Telegraph. Archived from the original on 3 September 2019. Retrieved 17 September 2019.
  67. ^ "18 buildings damaged as Kolkata Metro tunnel-borer 'hits aquifer'". Times of India. 2 September 2019. Archived from the original on 5 September 2019. Retrieved 17 September 2019.
  68. ^ "Railways Mulling to Flag-off Kolkata Metro East-West Corridor on 24 October". News18.com. 24 October 2019. Archived from the original on 22 October 2019. Retrieved 12 November 2019.
  69. ^ Chakraborty, Ajanta (26 November 2019). "Kolkata Metro asks for extension of Eest-West's November 30 deadline". The Times of India. Archived from the original on 29 November 2019. Retrieved 3 February 2020.
  70. ^ "India's first underwater metro expected to be complete by March 2022". www.businesstoday.in. 29 January 2020. Archived from the original on 30 January 2020. Retrieved 3 February 2020.
  71. ^ Chakraborty, Ajanta (3 February 2020). "East-West tunnelling disaster: Last group of seven moves to new flats from hotel". The Times of India. Archived from the original on 4 February 2020. Retrieved 3 February 2020.
  72. ^ "Kolkata Metro: High Court gives nod for resumption of East-West corridor work". Livemint. 11 February 2020. Archived from the original on 12 February 2020. Retrieved 11 February 2020.
  73. ^ "Cracks in houses on East-West Metro tunnel route". www.telegraphindia.com. Archived from the original on 28 February 2020. Retrieved 28 February 2020.
  74. ^ Chakraborty, Ajanta (18 June 2020). "West Bengal: East-West Metro's Phoolbagan extension gets CRS nod". The Times of India. Retrieved 8 July 2020.
  75. ^ Chakraborty, Ajanta (10 August 2020). "Good news in lockdown times: Metro completes India's deepest air shaft". The Times of India. Retrieved 10 August 2020.
  76. ^ Mondal, Suvodip (1 October 2020). "Agencies seek Friday-Sunday Sealdah flyover closure for East-West Metro tunnelling". The Times of India.
  77. ^ "Phoolbagan Metro station starts Monday". www.telegraphindia.com. Retrieved 4 October 2020.
  78. ^ "The Metro Station of Salt Lake Stadium will be known as IFA Salt Lake Stadium". Facebook.
  79. ^ "Tunnel boring machine reached Sealdah metro station" (in Bengali).
  80. ^ "Sealdah flyover opened to traffic 13 hours early". The Times of India.
  81. ^ Mondal, Biswadeep (5 January 2021). "Urvi starts bridging last 800m gap of E-W Metro tunnel". Times of India.
  82. ^ "Kolkata Metro Construction Leaves Cracks in Bowbazar Buildings And Residents' Morale". News18. 13 May 2022. Retrieved 16 March 2024.
  83. ^ Nag, Jayatri. "Sealdah station of Kolkata metro inaugurated". The Economic Times. Retrieved 14 July 2022.
  84. ^ "Kolkata Metro runs first underwater passenger trial run between Howrah Maidan and Esplanade". India Today. 21 April 2023. Retrieved 6 March 2024.
  85. ^ "Hope for ops start of three new Metro links in March first week". The Times of India. 19 February 2024. ISSN 0971-8257. Retrieved 21 February 2024.
  86. ^ "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 March 2024.
  87. ^ "India's deepest Metro station at Howrah also to be the largest". The Times of India. 1 March 2024. ISSN 0971-8257. Retrieved 8 March 2024.
  88. ^ "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 March 2024.
  89. ^ "Kolkata's Underwater Metro To be Open For Public From March 15: East West Metro Rail Corporation". TimesNow. 9 March 2024. Retrieved 16 March 2024.

[1]

External links

  1. ^ "Kolkata Metro Construction Leaves Cracks in Bowbazar Buildings And Residents' Morale". News18. 13 May 2022. Retrieved 16 March 2024.